Bathroom installation in solihull

Itinerary of how we work to install your new bathroom, duration is an example only and may vary depending on project size, type and complexity!

Day 1 & 2

 

  • Dust sheet protection installed

  • Skip arrives

  • Strip out the old bathroom

​

Days 3 & 4

 

  • New plumbing installed/modified

​

realistic-flag-auto-racing-inscription-s

Days 5 & 6

 

  • Floor boards made good

  • Walls/ceiling plaster boarded

​

Day 7

 

  • Plastering where required

​

Day 8, 9 & 10

 

  • Floor boarded over with ply wood

  • New bath or shower tray installed

  • Walls/ceiling painted

​

Day 11, 12, 13  & 14

 

  • Wall & floor tiling installed

​

Days 15, 16 & 17

 

  • Toilet/basin/radiator installed

  • Shower enclosure/bath screen installed

  • Anti-bacterial sealant applied

  • Sanitary ware commissioned

​

Day 18

 

  • Skip removed

​