Itinerary of how we work to install your new bathroom, duration is an example only and may vary depending on project size, type and complexity!
Day 1 & 2
-
Dust sheet protection installed
-
Skip arrives
-
Strip out the old bathroom
​
Days 3 & 4
-
New plumbing installed/modified
​
Days 5 & 6
-
Floor boards made good
-
Walls/ceiling plaster boarded
​
Day 7
-
Plastering where required
​
Day 8, 9 & 10
-
Floor boarded over with ply wood
-
New bath or shower tray installed
-
Walls/ceiling painted
​
Day 11, 12, 13 & 14
-
Wall & floor tiling installed
​